In rigging, which term refers to the fixed end of a rope or sling that remains stationary during the lift?

Prepare for your Rigger Safety Training Test. With multiple choice and flashcard questions, each complete with hints and explanations, you’ll be well-equipped to succeed!

Multiple Choice

In rigging, which term refers to the fixed end of a rope or sling that remains stationary during the lift?

Explanation:
In rigging, the standing part is the portion of rope that is fixed and remains stationary during the lift. This is the section that is anchored or tied off and does not move as you raise the load. The part you actually move to apply force or control the rope is the working end, which is the free end used to pull or adjust the line. The other terms describe different things: the load point is where the load attaches, and a sheave is the pulley wheel that the rope runs through. So the fixed, unmoving portion of the rope during a lift is the standing part.

In rigging, the standing part is the portion of rope that is fixed and remains stationary during the lift. This is the section that is anchored or tied off and does not move as you raise the load. The part you actually move to apply force or control the rope is the working end, which is the free end used to pull or adjust the line. The other terms describe different things: the load point is where the load attaches, and a sheave is the pulley wheel that the rope runs through. So the fixed, unmoving portion of the rope during a lift is the standing part.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy